  2. What do Home2 and Tru cost to build in 2026?
  3. Who lends on Home2 and Tru construction in 2026?
  4. How do lenders size a Home2 or Tru construction loan?
  5. What do lenders need to see on a Hilton new build?
  6. Worked example 1: a 107-suite Home2 Suites
  7. Worked example 2: a 98-room Tru by Hilton
  8. Worked example 3: a 200-key Home2 and Tru dual-brand
  9. When is a Home2 or Tru build the wrong tool?
  10. Frequently asked questions

A new Home2 Suites costs $18.1 million to $26.6 million for the 107-suite prototype and a new Tru by Hilton $14.3 million to $20.7 million for 98 rooms, both before land, according to Hilton's March 30, 2026 franchise disclosure documents. Owners finance them with a construction loan at 55% to 75% of cost, a C-PACE layer on the mechanical scope and 25% to 35% equity. Three kinds of lender write these builds in 2026: Bridge, which lends its own senior capital on Hilton construction from $10 million to $50 million; the banks and hotel debt funds that take the rest of the market; and, for owner-operators under about $15 million, SBA 504.

The brand data makes the case for both. Home2 is the best-performing select-service brand in the Hilton system, 78.0% occupancy and $112.63 RevPAR in 2025 with a 125.1 RevPAR index, and the most built, with 572 U.S. agreements signed and not yet open. Tru runs $91.27 of RevPAR at a lower cost per key, $146,000 to $211,000 against Home2's $169,000 to $248,000. This guide gives the costs, fees and performance, the lenders, the way a loan is sized, and three worked stacks: a Home2, a Tru and the 200-key dual-brand both brands' owners are building. Bridge's Hilton program is on its Hilton owner page.

Key takeaways

  • 2026 FDD costs before land: Home2 $169K to $248K per key (107 suites); Tru $146K to $211K (98 rooms).
  • 2025 performance: Home2 78.0% occupancy, $112.63 RevPAR, 125.1 index; Tru 71.2%, $91.27.
  • Fees: Home2 $100,000, 6% royalty, 3.5% program; Tru $100,000, 5.5%, 4%; 22-year term.
  • Bridge lends directly on Hilton construction $10M to $50M; closed $22M Home2 and $15.5M Tru loans.
  • Lenders size on stabilized NOI: a 107-suite Home2 at brand-average RevPAR supports about $14M of senior debt.

What do Home2 and Tru cost to build in 2026?

From the Home2 Suites 2026 FDD, which puts the 107-suite prototype at $18,075,688 to $26,550,592 before land and 2025 Item 19 at 78.0% occupancy, a $144.47 ADR and $112.63 RevPAR, with a 6% royalty and a 3.5% program fee, and the Tru by Hilton 2026 FDD, $14,258,164 to $20,659,558 for 98 rooms with 71.2% occupancy, a $128.20 ADR and $91.27 RevPAR, with a 5.5% royalty and a 4% program fee, both issued March 30, 2026. Item 7 excludes real property, and per-key figures are the totals divided by the prototype room counts.

Item

Home2 Suites

Tru by Hilton

Prototype

107 suites

98 rooms

Item 7 estimated initial investment (excluding land)

$18,075,688 to $26,550,592

$14,258,164 to $20,659,558

Per key

$168,900 to $248,100

$145,500 to $210,800

Paid to Hilton and affiliates

up to $245,471

up to $234,346

Application fee

$100,000

$100,000

Royalty / program fee

6.0% / 3.5% of gross room revenue

5.5% / 4.0%

Term

22 years from signing

22 years from signing

2025 Item 19 (comparable U.S. hotels)

78.0% occupancy, $144.47 ADR, $112.63 RevPAR, RevPAR index 125.1

71.2% occupancy, $128.20 ADR, $91.27 RevPAR

U.S. agreements signed, not open (YE2025)

572; 82 projected 2026 openings

230; 32 projected 2026 openings

Franchised system (June 30, 2026)

911 hotels / 100,689 rooms

340 hotels / 32,928 rooms

SBA Franchise Directory code

S0812

S1816

Two things to read into the table. Home2's low end rose about 15% from the 2025 FDD, more than the 4.8% trailing-twelve-month increase in HVS's construction cost indexes, so a 2025 budget is stale. Both brands sit near or below HVS's $170,000 to $197,000 median for limited-service and midscale extended-stay, which is why they lead the select-service pipeline. But the cheaper build is not always the better one: Tru's lower cost per key buys a $21 lower RevPAR, and on a site that supports Home2's rate the extra $23,000 per key earns its keep in the loan sizing below.

Who lends on Home2 and Tru construction in 2026?

Rank

Lender type

Loan-to-cost

Pricing (Oct 2026)

Recourse

Notes

1

Bridge (direct Hilton construction lending)

Up to 75%

Senior pricing from Bridge's own capital

Completion guaranty, carve-outs

$10M to $50M; closed a $22M Home2 in California and a $15.5M Tru in Florida; official Hilton capital partner

2

Regional and national banks

55-65%

6.25% to 7.25% (SOFR + 250-325)

Full repayment and completion guaranties

Lowest coupon; want a prior hotel and a relationship

3

Bank hotel franchise-finance desks

60-65%

About 6.75%

Recourse, burning off at coverage

Multi-unit Hilton owners

4

Hotel debt funds

70-75%; stretch to 80%

SOFR + 350-600 (7.5% to 10%+)

Non-recourse with carve-outs, completion guaranty

Speed and leverage

5

SBA 504 (owner-operators)

80-85% combined

6.97% fixed debenture; bank first about 7%

Personal guaranty

Debenture capped at $5.5M, so projects under about $15M

6

C-PACE (stack layer, any of the above)

15-25% of cost

High 6s to mid 7s fixed, 20-30 years

Non-recourse assessment

Senior consent required

Bridge closed more than $500 million of hotel loans in 2025, and the two Hilton construction closings above came from its own balance sheet. Market terms behind rows 2 to 4 are from the Crittenden 2026 hotel lending survey: banks at 65% of cost around 6.75% with coverage starting at 1.25x, debt funds at 70% near 10%.

How do lenders size a Home2 or Tru construction loan?

On the stabilized NOI, with loan-to-cost as the ceiling. Take the 107-suite Home2 at the brand's 2025 average: $112.63 RevPAR produces about $4.4 million of room revenue and $4.55 million in total; at a 40% margin after a 4% FF&E reserve, NOI is about $1.82 million. The three tests:

Test

2026 target

Loan supported

Debt yield

11% to 12%

$15.2M to $16.5M

Stabilized DSCR at a 7% perm rate, 25-year amortization

1.30x

$16.5M

Loan-to-cost on a $24M project

65%

$15.6M

Binding constraint

debt yield at 12%

about $15.2M

For a 98-room Tru at $91.27 RevPAR, revenue is about $3.26 million, NOI about $1.25 million at 38%, and the loan lands at $10.4 million to $11.4 million on the same tests, 60% to 65% of a $17.5 million project. The lesson is the same on both brands: the loan follows the NOI, so a site that beats the brand's 2025 average by 15% carries 70% leverage and a site that trails it carries 55%. The full checklist and draw mechanics are in hotel construction loans in 2026.

What do lenders need to see on a Hilton new build?

  1. The executed Hilton franchise agreement; approval takes 60 to 90 days, and Hilton's 2026 disclosure requires construction to start within 15 months of approval.
  2. A GMP contract with a bonded general contractor and a 10% to 15% contingency.
  3. A budget inside the FDD range.
  4. An STR competitive-set study and a pro forma that starts at or below Item 19.
  5. Sponsor liquidity of 10% to 20% of the loan after closing.
  6. A prior hotel or an experienced partner on the guaranty.
  7. The exit: a permanent loan sized on stabilized NOI, or a mini-perm.

Hilton issues a Lender Comfort Letter for $3,500 giving the lender notice and cure rights. Key money is discretionary and tilts to upscale brands, so a Home2 or Tru budget should not assume it; the fee concessions Hilton actually granted in 2025 are in Hilton franchise fees by brand.

Worked example 1: a 107-suite Home2 Suites

Building cost $21.5 million (mid-range of Item 7), land $1.8 million, $23.3 million all-in, $218,000 per key.

Layer

Amount

Share

Terms

Bridge direct construction loan or bank

$15.1M

65%

SOFR + 300 to 350 (6.9% to 7.4%); 24 to 36 months; perm at 7%

C-PACE assessment

$2.8M

12%

7.25% fixed, 25 years

Equity (including land)

$5.4M

23%

n/a

At $1.82 million of stabilized NOI, permanent debt service of about $1.28 million on the senior loan and $250,000 on the assessment gives 1.19x on the combined stack and a debt yield of about 12.1% on the senior. Most lenders will trim the senior to about $14.3 million for 1.25x combined, pushing equity to $6.2 million. At a 10% RevPAR premium to the brand's 2025 average ($124), NOI rises to $2.1 million and the original stack covers 1.37x.

Worked example 2: a 98-room Tru by Hilton

Building cost $17 million, land $1.2 million, $18.2 million all-in, $186,000 per key. Senior loan $11.4 million (63%) at about 7%, C-PACE $1.8 million, equity $5.0 million (27%). At $1.25 million of NOI the stack for this hotel does not quite close: $11.4 million at 7% on a 25-year amortization costs about $967,000 a year and the $1.8 million assessment at 7.25% about $156,000, so combined coverage is about 1.1x against the 1.25x most lenders want. Trimming the senior to about $10 million, 55% of cost, restores 1.25x and lifts equity to $6.4 million; the 11% debt yield test holds at either size. Bridge's $15.5 million loan on a 106-key Tru is the live comparable: a larger building in a stronger Florida market, financed at a higher absolute loan on higher NOI.

Worked example 3: a 200-key Home2 and Tru dual-brand

Dual-brand builds share the lobby, back of house and site, which is why owners combine them. A 110-suite Home2 and a 90-room Tru at a combined $36 million building cost and $2.5 million of land is $38.5 million, about $192,500 per key, about 5% to 7% under the two single-brand budgets added together. Combined stabilized NOI of about $3.0 million (Home2 at $112.63, Tru at $91.27) supports a $25 million senior loan at a 12% debt yield, 65% of cost, with a $4.5 million C-PACE layer and $9 million of equity. Lenders treat the dual-brand as one credit with two franchise agreements, and the blended RevPAR index above 110 is what gets the leverage to 65% in the example above. The economics across the extended-stay brands are compared in Home2 vs Tru vs Everhome vs Hyatt Studios.

When is a Home2 or Tru build the wrong tool?

  • Avoid a Home2 on a site under about $95 of RevPAR. At $218,000 per key the stack covers only on NOI near the brand average or better.
  • Avoid a Tru in a market with an existing Home2 inside five miles unless the dual-brand is yours; the brands share demand.
  • Avoid SBA 504 above about $15 million of cost. The $5.5 million debenture cap makes the structure too thin.
  • Avoid budgeting from the 2025 FDD. Home2's low end moved 15% in one year.
  • Avoid starting without the executed agreement. Lenders will not underwrite brand-driven hard costs on a letter of intent, and Hilton's 15-month start clock runs from approval.

Frequently asked questions

How much does it cost to build a Home2 Suites?

Hilton's March 2026 FDD estimates $18,075,688 to $26,550,592 for the 107-suite prototype, excluding land, which is $168,900 to $248,100 per key. With land and an interest reserve most projects land at $200,000 to $270,000 per key all-in. The low end rose about 15% from the 2025 FDD, so budget from the current document, not last year's.

How much does it cost to build a Tru by Hilton?

$14,258,164 to $20,659,558 for the 98-room prototype before land per the 2026 FDD, or $145,500 to $210,800 per key, roughly 15% less than a Home2 per key. Tru's 2025 RevPAR of $91.27 is about 19% below Home2's $112.63. Add land, contingency and an interest reserve, all of which Item 7 excludes, before sizing the loan.

How do owners finance a Home2 or Tru new build?

With a construction loan at 55% to 75% of cost from Bridge, a bank or a hotel debt fund, a C-PACE assessment on 12% to 25% of cost, and 25% to 35% equity; owner-operators under about $15 million of cost can use SBA 504 at 15% to 20% equity. Bridge lends directly on Hilton construction from $10 million to $50 million and closed a $22 million Home2 loan and a $15.5 million Tru loan.

What do lenders need to see for a Home2 or Tru construction loan?

The executed Hilton franchise agreement, a GMP contract with a bonded contractor and 10% to 15% contingency, a budget inside the FDD range, an STR study and a pro forma at or below the brand's 2025 Item 19, 10% to 20% post-closing liquidity, hotel experience on the guaranty, and a written takeout. Hilton's Lender Comfort Letter costs $3,500.

Is a Home2 and Tru dual-brand cheaper to build?

Usually 5% to 10% per key, because the two brands share the lobby, back of house, parking and site work; a 200-key dual-brand at about $192,500 per key compares with $218,000 for a stand-alone Home2. Lenders underwrite it as one credit with two franchise agreements and give leverage to a blended RevPAR index above 110.